Provo, UT permit fees and requirements

Provo prices building permits from project valuation on the 1997 UBC Table 1-A chart:

$23.50 to $500, then per-$100 and per-$1,000 rates stepping from $14.00 per $1,000 down to $3.15 per $1,000 — with plan review at 65% of the permit fee and a 1% state fee.

Verified Sep 2026

Permit costs we have worked out

Each page shows the fee components, the formula the jurisdiction uses, and a worked example you can follow by hand.

Estimate your potential Provo permit fee with our Building Permit Fee Calculator.

Permit pages for Provo
PermitCategoryLast reviewed
Provo building permit feesstructural2026-09-26
Provo electrical permit feeselectrical2026-09-26
Provo plumbing permit feesplumbing2026-09-26

Local context

What is specific to Provo

Provo's own fee prose is short and stable: the Consolidated Fee Schedule's Inspection Fees section says the building permit is 'based on the 1997 UBC Fee Chart,' and the City's FAQ repeats the mechanism — permit cost based on construction valuation, read from a table found in the 1997 UBC, plan check at 65%, plus a 1% state fee sent to the state for training. That makes the 1997 Uniform Building Code's Table 1-A the operative chart, and its rows chain exactly: $23.50 flat to $500; $23.50 + $3.05 per $100 to $2,000 ($69.25 at the seam); $69.25 + $14.00 per $1,000 to $25,000 ($391.25); $10.10 per $1,000 to $50,000 ($643.75); $7.00 per $1,000 to $100,000 ($993.75); $5.60 per $1,000 to $500,000 ($3,233.75); $4.75 per $1,000 to $1,000,000 ($5,608.75); then $3.15 per $1,000 above.

One bundling rule matters for houses: for residential structures with not more than 4 units, the building permit fee includes the plumbing, electrical and mechanical permit fees. Stand-alone trade permits file at the printed minimums — $75.00 for electrical and plumbing inspection (Commercial Electrical $175.00), with plumbing fixtures priced $20.00 for the first and $6.00 each after.

Building Inspection sits at 351 West Center Street and runs plan review at 65% of the permit fee; valuation itself follows International Code Council Building Valuation Data, which the schedule names directly.

Valuation

How valuation is determined here

Project valuation (per ICC Building Valuation Data) read against the 1997 UBC Table 1-A chart: $23.50 flat to $500, $3.05 per $100 to $2,000, $14.00 per $1,000 to $25,000, $10.10 per $1,000 to $50,000, $7.00 per $1,000 to $100,000, $5.60 per $1,000 to $500,000, $4.75 per $1,000 to $1,000,000, then $3.15 per $1,000. Each partial increment rounds up.

Who to contact

The office that issues the permit, with the details we have verified. Confirm current hours before travelling.

Building Inspection Division

Phone
(801) 852-6410
Hours
Monday through Friday, 7:00 a.m. to 6:00 p.m.

Official website

What these fees do not include

The list is not a disclaimer: on a new house the fees left out can outweigh the permit fee several times over. Every entry here is stated on the permit page as well.

Not included in our estimates

These figures are the permit fees the City's schedule and the 1997 UBC chart print. They exclude:

  • The 1% state fee on the building permit fee, which the FAQ documents as a state assessment for inspector and contractor training.
  • Impact fees (transportation, water, sewer, stormwater, public safety, parks), which Provo charges from separate schedules.
  • Mechanical permits ($75.00 minimum, $175.00 commercial) beyond the summary here.
  • Development-review and engineering fees from other sections of the Consolidated Fee Schedule.

Official sources for this jurisdiction

The documents these figures are transcribed from. Where a source contradicts itself we keep both readings and say so on the permit page.

  • Municipal codeAuthorityPrimary source

    1997 UBC Table 1-A Building Permit Fee Schedule (verbatim adoption)

    International Conference of Building Officials (ICBO) · Document dated January 1, 1997 · Effective July 1, 2021 · Retrieved September 26, 2026

    The 1997 UBC Table 1-A ladder Provo's schedule adopts: $23.50 to $500; $23.50 + $3.05/$100 to $2,000; $69.25 + $14.00/$1,000 to $25,000; $391.25 + $10.10/$1,000 to $50,000; $643.75 + $7.00/$1,000 to $100,000; $993.75 + $5.60/$1,000 to $500,000; $3,233.75 + $4.75/$1,000 to $1,000,000; $5,608.75 + $3.15/$1,000 above. Transcribed verbatim from a municipal code adopting the table; band bases chain exactly.

  • City websiteCityPrimary source

    Provo Building Division

    Provo City Building Inspection Division · Document dated September 26, 2026 · Effective July 1, 2021 · Retrieved September 26, 2026

    The issuing office (351 West Center Street, 801-852-6410): permit applications, inspections and contractor resources.

  • Municipal codeCityPrimary source

    Provo City Consolidated Fee Schedule — Inspection Fees

    Provo City Corporation · Document dated September 26, 2026 · Effective July 1, 2021 · Retrieved September 26, 2026

    Read 2026-09-26 via text extraction proxy (direct fetch 403). Inspection Fees: 'Building permit — Based on the 1997 UBC Fee Chart. Building Valuation — Based upon International Code Council Building Valuation Data. Plan review — 65% of the Building Permit Fee.' Trade rows: Electrical Inspection $75, Commercial Electrical $175, Mechanical minimum $75, Commercial Mechanical $175, Plumbing minimum $75 with first fixture $20 / additional $6 / water heater $6. 'For residential structures with not more than 4 units the building permit fee includes the plumbing, electrical, and mechanical permit fees.'

  • City websiteCityPrimary source

    provo.gov FAQ — building codes and permit cost basis

    Provo City Corporation · Document dated September 26, 2026 · Effective July 1, 2021 · Retrieved September 26, 2026

    'The permit cost is based on the cost (valuation) of the construction. We use a table found in the 1997 UBC to assess the permit fees. A plan check fee of 65% of the building permit fee is charged. A state fee of 1% of the building permit fee is charged and sent to the state for training of inspectors and contractors.'